The overall project comprised the installation of a temporary sports hall. The foundations were installed using specialist formwork due to the ground levels. The temporary building was made from an aluminum frame, installed wall panels and a twin walled PVC roof that was inflated on site. The frame and components were produced off site and then built on site.
The flooring installed is a metal cassette mezzanine floor that used OSB board and plywood on top and then finished using Tarkett Sports Flooring to complete it. We also installed Fermosel Walling to create a sports wall specification, this comprised of metal studwork and two layers of Fermosel boards to the Sports Hall side and a single layer to the reception side with acoustic insulation in between.
A reception area was also installed. The overall project was completed in 8 weeks.